Construction Package 7

Package No : CP-7

Name of EPC Contractors : M/s. Reliance Infrastructure Ltd.

Length in Km: 51.190

LOA Issued date : 30.08.2018

Chainage details : Package 7, From Km. 296.000 to Km. 347.190 (Section – Village Banda to Village Sawargaon Mal) in District Buldhana

Name of Authority Engineers Consultant : M/s. LN Malviya Infra Projects Pvt. Ltd. In J/v with Highway Engineering Consultant

LOA Issued date : 26.11.2018

Description

Scope

WIP

Completed

Major Structures

Flyover/Viaduct

09

01

Major Bridges

04

Minor Structures

Minor Bridges

17

03

VOP

04

VUP

10

03

LVUP

01

01

CUP and PUP

18

14

01

POP

11

Box Culverts

32

04

28

Other Structures

Interchanges

02

Total Structure

105

29

29

May 2020

April 2020

March 2020

February 2020

January 2020

December 2019

November 2019

October 2019

September 2019

August 2019

July 2019