Construction Package 5

Package No : CP-5

Name of EPC Contractors : M/s. Sadbhav Engineering Ltd.

Length in Km: 42.877

LOA Issued date : 30.08.2018

Chainage details : Package 5, From Km. 217.023 to Km. 259.900 (Section – Village Kinhiraja to Village Kenwad) in District Washim

Name of Authority Engineers Consultant : M/s. Lion Engineering Consultants

LOA Issued date : 17.10.2018

Description

Scope

WIP

Completed

Major Structures

Flyover/Viaduct

12

Major Bridges

02

02

ROB

01

Minor Structures

Minor Bridges

09

06

01

VOP

04

VUP

07

02

LVUP

04

CUP and PUP

15

05

01

WOP

02

POP

04

Box Culverts

23

08

01

Other Structures

Interchanges

01

Total Structure

83

25

03

May 2020

April 2020

March 2020

February 2020

January 2020

December 2019

November 2019

October 2019

September 2019

August 2019

July 2019