Construction Package 2
Package No : CP-2
Name of EPC Contractors : M/s. Afcon Infrastructure Ltd.
Length in Km: 58.413
LOA Issued date : 30.08.2018
Chainage details : Package 2, from Km. 31.000 to Km. 89.413 (Section – Village Khadki Amgaon to Village Pimpalgaon) in District Wardha
Name of Authority Engineers Consultant :M/s. Consulting Engineers Group Ltd. in association with SKES
LOA Issued date : 17.10.2018
Description
Scope
WIP
Completed
Major Structures
Flyover/Viaduct
08
05
02
Major Bridges
03
03
–
ROB
02
01
–
Minor Structures
Minor Bridges
17
12
04
VOP
2
–
–
VUP
19
05
13
Canal Bridge
07
05
02
Box Culverts
81
14
57
Other Structures
Interchanges
02
–
–
Total
153
48
87